Royal ISD HS – Package 02 (GMP)

Final GMP Pricing for Package 02 -  Package 02 for the New Royal High School project will include:
  • Site & Building Concrete
  • Structural Steel Fabrication & Erection

All bids must be submitted to: [email protected]

Estimator: Julian Ciarella

Estimated Start Date: June 10, 2026

Estimated End Date: July 6, 2028

Project Value: $215,000,000.00

Project Site: 5111 FM 362, Brookshire, TX , 77423

Bid: June 24, 2026 2:00 pm

Bid Type: CM@R

Contact the Estimator